List of steps
(Total number of steps: 71)
Meet IPA
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies for land and infrastructure lease  (2)
Lease infrastructure inside industrial zone  (1)
Obtain authenticated copies for investment certificate application  (2)
Declare investment project information online
Obtain investment registration certificate  (2)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain seal and seal registration certificate  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain cadastral map of investment site  (3)
Obtain fully-signed cadastral map  (4)
Pay costs for land clearance  (2)
Obtain authenticated copies of cadastral map and certified payment order  (2)
Obtain decision on land recovery and lease  (2)
Attend on-site title plan verification  (1)
Obtain authenticated copies for land lease contract application  (2)
Sign land lease contract  (2)
Obtain authenticated copies of land lease contract  (2)
Obtain land use right certificate  (4)
Obtain approval of environmental impact assessment (EIA) report  (6)
Obtain authenticated copies of land use right certificate, EIA  (2)
Obtain construction design profile  (2)
Obtain appraisal on construction design profile  (2)
Obtain fire prevention and fighting (FPF) profile  (2)
Obtain certificate of fire prevention and fighting approval  (2)
Obtain construction permit  (2)
Make seal and notify seal specimen  (2)
70
Make seal

Preview & Print

Properties
 
52
Sign service contract for EIA report
(last modified: 1/20/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

VND 15000000
0 mn  -  0 mn
30 days  -  45 days

Contact details

Entity in charge

Any consulting entities allowed to make EIA


List of EIA consulting entities in Vinh Phuc (not exhaustive) List of EIA consulting entities in Vinh Phuc (not exhaustive)

Expected results

Signed service contract for EIA profile Signed service contract for EIA profile
Payment receipt (EIA) 01 - Payment receipt (EIA)

Requirements

1. 01 - Libre deuda de patente
Authenticated copy of approval for investment intent (an authentic copy)
or Authenticated copy of investment certificate***
Authenticated copy of investment certificate***
2. Statement/ Presentation on investment project
Statement/ Presentation on investment project (Simple copy)
prepared by investors

Costs

Cost detail

Hypothesis

VND 15,000,000
Service fee for drafting EIA report - For reference only
Upon signing service contract, investor/company shall pay an advance of 50% of service fee as indicated in the contract.

Time frame

Attention at counter: Min. 30mn - Max. 1h
Waiting time until next step: Min. 30 days - Max. 45 days

Legal justification

1. Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
articles 18, 19, 20
2. Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 12, 13, 14, 15, 16, 17, 40, Appendixes
3. Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 10, 12

Additional information

Projects required to make Environment Impact Assessment (EIA) report are listed in Appendix II, Decree 29/2011/ND-CP. The EIA report must be approved by the provincial people’s committee. Exceptions are made for the projects that are approved by the Ministry of Natural Resources and Environment which are listed in Appendix III, Decree 29/2011/ND-CP.

Regarding other projects, investors have to make and register the environment protection commitment in written form to the district-level People’s Committee where the project is located.

We only describe here the procedures on making and requesting for approval of EIA report at Vinh Phuc People’s Committee.

Investor/company should contact to any consultancy company which has acquired legally-recognized functions, as stipulated in Article 8, Decree 29/2011/ND-CP, to prepare EIA report on investor's behalf.
List of projects subject to environmental impact assessment reporting List of projects subject to environmental impact assessment reporting