Requirements
1.
Land use right certificate* (original + 5 simple copies)
2.
Decision on EIA approval (original + 3 simple copies)
Time frame
If the document(s) is submitted at 15:00 hrs or afterwards, the result shall be issued the next day.
Waiting time in queue:
Min. 5mn - Max. 20mn
Attention at counter:
Min. 5mn - Max. 10mn
Waiting time until next step:
Max. 1 day
Legal justification
1.
Decree No. 79/2007/ND-CP of the Government dated May 18, 2007 on the issue of copies from master registers, authentication copies from originals, authentication of signatures
articles 5, 13, 14, 15
2.
Decree No. 04/2012/ND-CP of the Government dated January 20, 2012 amending and supplementing article 5 of the Government’s Decree No. 79/2007/ND-CP dated May 18, 2007 on the issue of copies from master registers, authentication copies from originals, authentication of signatures
Article 1
3.
Circular No.03/2008/TT-BTP of the Ministry of Justice dated August 3, 2008 guiding the implementation of a number of article of the Governments Decree No. 79/2007/ND-CP dated May 18, 2007, on the issue of copies master registers, authentication of copies from originals, authentication of signatures
Article 1
Additional information
Investors can do the procedure for document authentication at any People's Committee in any district/town/commune in Vinh Phuc as stipulated by Article 01 of Circular No. 03/2008/TT-BTP.
Because it is required to file a copy of each document by the unit in charge, the applicant must logde at least two copies of each document, including: 1 copy for filling and at least 1 copy (or more subject to the investor's demand on each type of document) for authenticating and returning to investor.