List of steps
(Total number of steps: 71)
Meet IPA
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies for land and infrastructure lease  (2)
Lease infrastructure inside industrial zone  (1)
Obtain authenticated copies for investment certificate application  (2)
Declare investment project information online
Obtain investment registration certificate  (2)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Obtain seal and seal registration certificate  (2)
Obtain certificate of tax registration  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain cadastral map of investment site  (3)
Obtain fully-signed cadastral map  (4)
Pay costs for land clearance  (2)
Obtain authenticated copies of cadastral map and certified payment order  (2)
Obtain decision on land recovery and lease  (2)
Attend on-site title plan verification  (1)
Obtain authenticated copies for land lease contract application  (2)
Sign land lease contract  (2)
Obtain authenticated copies of land lease contract  (2)
Obtain land use right certificate  (4)
Obtain approval of environmental impact assessment (EIA) report  (6)
Obtain authenticated copies of land use right certificate, EIA  (2)
Obtain construction design profile  (2)
Obtain appraisal on construction design profile  (2)
Obtain fire prevention and fighting (FPF) profile  (2)
Obtain certificate of fire prevention and fighting approval  (2)
Obtain construction permit  (2)
Make seal and notify seal specimen  (2)
70
Make seal

Preview & Print

Properties
 
65
Collect FPF profile
(last modified: 1/20/2017)

Contact details

Entity in charge

Any fire prevention and fighting design consultant

Vinh Phuc Province

Expected results

Document handover confirmation (for FPF profile) x2 01 - Document handover confirmation (for FPF profile)
FPF design profile x6 01 - FPF design profile
Result acceptance confirmation 01 - Result acceptance confirmation
FPF design service contract liquidation x4 FPF design service contract liquidation
VAT invoice (for FPF profile) 01 - VAT invoice (for FPF profile)

Costs

As soon as document handover confirmation is signed, the company/investor shall pay the balance of contract service fee to the consultant subject to the service contract terms.

Time frame

Attention at counter: Min. 30mn - Max. 1h