List of steps
(Total number of steps: 79)
Meet IPA
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies of approval of investment intent  (2)
Obtain endorsement of investment site map  (4)
Obtain approval of investment site  (2)
Obtain authenticated copies of documents  (2)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
29
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (6)
Obtain cadastral map of investment site  (2)
Obtain land recovery acceptance of Commune People's Committee  (3)
Obtain proposal of compensation and resettlement plan  (2)
Obtain authenticated copies for land recovery acceptance file  (2)
Obtain land recovery acceptance of District People's Committee  (2)
Obtain authenticated copies for land recovery and lease application file  (2)
Obtain decision on land recovery and lease  (2)
Obtain approval of compensation and resettlement plan  (1)
Pay compensation and support amounts  (1)
Attend on-site title plan verification  (1)
Obtaining authenticated copies for land lease contract application  (2)
Sign land lease contract  (2)
Obtain authenticated copies of land lease contract  (2)
Obtain planning certificate  (2)
Obtain land use right certificate (LURC)  (4)
Obtain construction design profile  (2)
Obtain appraisal on construction design profile  (2)
Obtain authenticated copies of planning certificate, LURC and approval of EIA report  (2)
Obtain fire prevention and fighting (FPF) profile  (2)
Obtain certificate of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
40
Obtain land recovery notice
(last modified: 1/20/2017)

Contact details

Entity in charge

Any District People's Committees


List of People's Committees List of People's Committees

Expected results

Land recovery notice Land recovery notice

Requirements

1. 01 - Libre deuda de patente
Authenticated copy of approval of investment site
2. 01 - Libre deuda de patente
Planning map endosed by Province People's Committee (original)

Time frame

Investor shall receive an original copy of the notice on land acquisition sent by the district People’s Committee via post possibly within 5 working days after the issuance of the notice.
Attention at counter: Min. 10mn - Max. 15mn

Legal justification

1. Law on Land No. 13/2003/QH11 dated 26 Nov 2003_EN
Law on Land No. 13/2003/QH11 dated 26 Nov 2003_EN
Article 39.2
2. Decree No. 69/2009/ND-CP dated 13 Aug 2009_EN
Decree No. 69/2009/ND-CP dated 13 Aug 2009_EN
Article 29.2
3. Circular No. 14/2009/TT-BTNMT dated 01 Oct 2009_EN
Circular No. 14/2009/TT-BTNMT dated 01 Oct 2009_EN
Article 26

Additional information

This step is applicable to the case of projects located within only one (1) district, town or provincial city. For the case of projects located in two (2) or more districts, towns or provincial cities, please refer to the step no. o following this step.

Any time after the decision on approval of investment location, investor could start preparing and carry out to submit application for obtaining land recovery notice of the district People's Committee.

Within 04-05 working days as from the date of receipt of required application, the Division of Natural Resources and Environment under district People's Committee shall issue and publicize land recovery notice through mass media.

The Division also publicly posts the notice at the headoffice of the People's Committees of the commune where the requested land plot is located and at a place for community activities of the commune.

This step is done at the People's Committee of any district where project site is located. The example herein demonstrates practices at the People's Committee of Vinh Yen City for reference.