List of steps
(Total number of steps: 79)
Meet IPA
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies of approval of investment intent  (2)
Obtain endorsement of investment site map  (4)
Obtain approval of investment site  (2)
Obtain authenticated copies of documents  (2)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
29
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (6)
Obtain cadastral map of investment site  (2)
Obtain land recovery acceptance of Commune People's Committee  (3)
Obtain proposal of compensation and resettlement plan  (2)
Obtain authenticated copies for land recovery acceptance file  (2)
Obtain land recovery acceptance of District People's Committee  (2)
Obtain authenticated copies for land recovery and lease application file  (2)
Obtain decision on land recovery and lease  (2)
Obtain approval of compensation and resettlement plan  (1)
Pay compensation and support amounts  (1)
Attend on-site title plan verification  (1)
Obtaining authenticated copies for land lease contract application  (2)
Sign land lease contract  (2)
Obtain authenticated copies of land lease contract  (2)
Obtain planning certificate  (2)
Obtain land use right certificate (LURC)  (4)
Obtain construction design profile  (2)
Obtain appraisal on construction design profile  (2)
Obtain authenticated copies of planning certificate, LURC and approval of EIA report  (2)
Obtain fire prevention and fighting (FPF) profile  (2)
Obtain certificate of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
32
Sign service contract for EIA report
(last modified: 1/20/2017)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

VND 15000000
0 mn  -  0 mn
30 days  -  45 days

Contact details

Entity in charge

Any consulting entities allowed to make EIA


List of EIA consulting entities in Vinh Phuc (not exhaustive) List of EIA consulting entities in Vinh Phuc (not exhaustive)

Expected results

Signed service contract for EIA profile Signed service contract for EIA profile
Payment receipt (EIA) 01 - Payment receipt (EIA)

Requirements

1. 01 - Libre deuda de patente
Authenticated copy of approval for investment intent (an authentic copy)
or Authenticated copy of investment certificate***
Authenticated copy of investment certificate***
2. Statement/ Presentation on investment project
Statement/ Presentation on investment project (Simple copy)
prepared by investors

Costs

Cost detail

Hypothesis

VND 15,000,000
Service fee for drafting EIA report - For reference only
Upon signing service contract, investor/company shall pay an advance of 50% of service fee as indicated in the contract.

Time frame

Attention at counter: Min. 30mn - Max. 1h
Waiting time until next step: Min. 30 days - Max. 45 days

Legal justification

1. Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
Law No. 52/2005/QH11 of the National Assembly on Environmental Protection
articles 18, 19, 20
2. Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Decree No. 29/2011/ND-CP of the Government dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 12, 13, 14, 15, 16, 17, 40, Appendixes
3. Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
Circular No. 26/2011/TT-BTNMT of the Ministry of Natural Resources and Environment detailing a number of articles of the Government’s Decree No. 29/2011/ND-CP dated April 8, 2011 on strategic environmental assessment, environmental impact assessment and environmental protection commitment
articles 10, 12

Additional information

Projects required to make Environment Impact Assessment (EIA) report are listed in Appendix II, Decree 29/2011/ND-CP. The EIA report must be approved by the provincial people’s committee. Exceptions are made for the projects that are approved by the Ministry of Natural Resources and Environment which are listed in Appendix III, Decree 29/2011/ND-CP.

Regarding other projects, investors have to make and register the environment protection commitment in written form to the district-level People’s Committee where the project is located.

We only describe here the procedures on making and requesting for approval of EIA report at Vinh Phuc People’s Committee.

Investor/company should contact to any consultancy company which has acquired legally-recognized functions, as stipulated in Article 8, Decree 29/2011/ND-CP, to prepare EIA report on investor's behalf.
List of projects subject to environmental impact assessment reporting List of projects subject to environmental impact assessment reporting