List of steps
(Total number of steps: 79)
Meet IPA
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passports or Vietnamese ID cards  (2)
Obtain approval of investment intent  (2)
Obtain authenticated copies of approval of investment intent  (2)
Obtain endorsement of investment site map  (4)
Obtain approval of investment site  (2)
Obtain authenticated copies of documents  (2)
Declare investment project information online
Obtain investment registration certificate (IRC)  (2)
Obtain authenticated copies of IRC  (2)
Obtain Enterprise Registration Certificate (ERC)  (3)
Make seal and notify seal specimen  (2)
29
Make seal
Open bank account  (1)
Obtain approval of environmental impact assessment (EIA) report  (6)
Obtain cadastral map of investment site  (2)
Obtain land recovery acceptance of Commune People's Committee  (3)
Obtain proposal of compensation and resettlement plan  (2)
Obtain authenticated copies for land recovery acceptance file  (2)
Obtain land recovery acceptance of District People's Committee  (2)
Obtain authenticated copies for land recovery and lease application file  (2)
Obtain decision on land recovery and lease  (2)
Obtain approval of compensation and resettlement plan  (1)
Pay compensation and support amounts  (1)
Attend on-site title plan verification  (1)
Obtaining authenticated copies for land lease contract application  (2)
Sign land lease contract  (2)
Obtain authenticated copies of land lease contract  (2)
Obtain planning certificate  (2)
Obtain land use right certificate (LURC)  (4)
Obtain construction design profile  (2)
Obtain appraisal on construction design profile  (2)
Obtain authenticated copies of planning certificate, LURC and approval of EIA report  (2)
Obtain fire prevention and fighting (FPF) profile  (2)
Obtain certificate of fire prevention and fighting  (2)
Obtain construction permit  (2)

Preview & Print

Properties
 
43
Submit application for setting up compensation council by District People's Committee
(last modified: 1/20/2017)

Contact details

Entity in charge

Any District People's Committee


List of People's Committees List of People's Committees

Expected results

Decision on establishment of compensation council Decision on establishment of compensation council

Requirements

1. Authenticated copy of investment certificate***
Authenticated copy of investment certificate***
2. 01 - Libre deuda de patente
Authenticated copy of approval for investment intent
3. 01 - Libre deuda de patente
Authenticated copy of approval of investment site
4. 01 - Libre deuda de patente
Planning map endosed by Province People's Committee (original)
5. 01 - Libre deuda de patente
Cadastral map certified by Commune People's Committtee (Simple copy)
6. Appointment letter to its representatives for setting up compensation council
Appointment letter to its representatives for setting up compensation council (original)
The Compensation Council which is in charge of compensation to and support for resettlement of the land users having been residing on the requested land plot.

Costs

Time frame

Within 05-07 working days as from the date of submision, a decision on establishment of compensation council shall be issued by the District People's Committee. Company/investor may receive this decision at any convenient time for its knowledgement.
Attention at counter: Min. 15mn - Max. 20mn

Legal justification

1. Decree No. 69/2009/ND-CP dated 13 Aug 2009_EN
Decree No. 69/2009/ND-CP dated 13 Aug 2009_EN
articles 25, 29.3.b, 29.5, 30
2. Decision No. 18/2011/QD-UBND dated 20 Apr 2011_VI
Decision No. 18/2011/QD-UBND dated 20 Apr 2011_VI
articles 29, 32.2, 32.3

Additional information

Investor has option to appoint its representative(s) to participate to Compensation Council to mediate, reach agreement on and finalize all the compensation for, and support to resettlement of existing land user(s) of the land plot in order to acquire that land plot. In fact, in most cases, investor appoints at least 03 representatives as members of Compensation Council (always including an accountant).

This step is applicable to the case of projects located within only one (1) district, town or provincial city. For the case of projects located in two (2) or more districts, towns or provincial cities, please refer to the step no. 0 following this step.

This step is done at the People's Committee of any district where project site is located. The example herein demonstrates practices at the People's Committee of Vinh Yen City for reference.
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License