Requirements
1.
Signed land lease contract (VPID) (original + 4 simple copies)
2.
Meeting minutes of on-site tittle plan verification (original + 2 simple copies)
Time frame
If the document(s) is submitted at 15:00 hrs or afterwards, the result shall be issued the next day.
Waiting time in queue:
Min. 5mn - Max. 20mn
Attention at counter:
Min. 5mn - Max. 10mn
Waiting time until next step:
Max. 1 day
Legal justification
1.
Decree No. 79/2007/ND-CP of the Government dated May 18, 2007 on the issue of copies from master registers, authentication copies from originals, authentication of signatures
articles 5.1.a, 13, 15
2.
Decree No. 04/2012/ND-CP of the Government dated January 20, 2012 amending and supplementing article 5 of the Government’s Decree No. 79/2007/ND-CP dated May 18, 2007 on the issue of copies from master registers, authentication copies from originals, authentication of signatures
Article 1
3.
Circular No.03/2008/TT-BTP of the Ministry of Justice dated August 3, 2008 guiding the implementation of a number of article of the Governments Decree No. 79/2007/ND-CP dated May 18, 2007, on the issue of copies master registers, authentication of copies from originals, authentication of signatures
Article 1
Additional information
Investors can do the procedure for document authentication at any People's Committee in any district/town/commune in Vinh Phuc as stipulated by Article 01 of Circular No. 03/2008/TT-BTP.
Because it is required to file a copy of each document by the unit in charge, the applicant must lodge at least two copies of each document, including: 01 copy for filling and at least 01 copy (or more subject to the investor's demand on each type of document) for authenticating and returning to investor.
The example herein demonstrates practices at the Vinh Yen People's Committee for reference.